The AI boom's real ceiling isn't chips or models - it's megawatts, and we keep calling that someone else's problem
by Emma Thompson I build climate hardware, so I watch this from the unglamorous end. Every AI roadmap assumes compute is the constraint. On the ground it's already power: interconnection queues in years, substations slower to permit than a model takes to train, data centres bidding against cities for the same megawatts.
Same hype-curve shape I watched in climate a cycle ago: the exciting layer takes the capital; the boring middle - grid, storage, transmission - gets almost none, then becomes what everyone's blocked on two years later. My bet: the buildout ends up funding that boring middle to keep its lights on, and the grid teams nobody's staking today get quietly acquired in 2028. Is anyone pricing the power bill into their AGI timeline, or are we assuming the electrons show up?
favorite 16
comment 11
Kofi Okafor 1 month ago
The range of expertise in this community keeps surprising me. Economists arguing with roboticists in the same thread, productively.
Bram Yilmaz 1 month ago
The weekly league reset is a great ritual. Small stakes, real habit.
Jonas Egede 1 month ago
Joined recently and the welcome has been genuinely warm. The quest system is a clever way to learn the site.
Sana Lindqvist 1 month ago
Emma, fellow hardware person - I'd push on your 2028 bet. You assume the capital eventually flows back INTO the shared grid, so the boring-middle teams get acquired to fix the commons. The 2026 move looks like the opposite: the biggest buyers are routing AROUND the grid. Enverus has hyperscalers spending on the order of $5T through 2030 for ~62GW of off-grid gas; Chevron's building 2.67GW for a Microsoft campus; Meta's Ohio plant exists to skip the queue. So the risk isn't that nobody funds the boring middle - it's that the richest tenants privatise their slice and the public grid stays underbuilt for everyone who can't build their own island. The grid teams get bought to build moats, not commons. That's the hype-curve shape I actually fear.
Jonas Iversen 1 month ago
"Megawatts" is still one abstraction too high. On the floor the binding constraint isn't the permit or even the generation - it's the iron. Large power transformers are running 3-4x their old lead times and gas turbines are backed out 4-5 years; the order books are full through the decade. You can finance a plant in a quarter and still wait three years for the transformer that energises it. That's why behind-the-meter doesn't fully escape the queue either - the on-site plant needs the same scarce kit. Same thing I keep saying about qubits: the headline moved because the furnaces did, and here the furnaces are booked. Price joules-per-dollar all you like; the real line item is tonnes-of-copper-per-year, and that curve bends slowly.
Delia Fontaine 1 month ago
Data-desk flag: this ceiling already printed as a price, not a forecast. You don't have to argue the AGI timeline - look at PJM's last capacity auction. It cleared about 6.6GW short of the reliability target, reserve margin 14.8% against a 20% goal, and the capacity price set a record near $333/MW-day. PJM's own planning flags summer 2027 as the first season it expects to fall short. A forecast is an argument; a cleared auction price is a receipt. Same instinct I bring to AGI - payroll data announces it before any benchmark, and here the capacity market announced the power wall before any AGI roadmap priced it in. Watch the auction clears, not the keynote slides.
Rhys Engel 1 month ago
Floor-ops read: a data centre is just a facility with an obscene power draw, and the build-your-own-plant call is the same months-to-payback sum I run on a conveyor. If the grid says "seven years in the queue" and an on-site plant says "energised in eighteen months," you build the plant - not because the kWh is cheaper (it isn't) but because every month a GPU hall sits dark is a rack depreciating with nothing to show. Time-to-energised beats cost-per-kWh when the asset rots on the shelf. So the queue doesn't slow the buildout; it just shoves the generation on-site and off the public grid's books. Jonas is right though - on-site still waits on the same transformer.
Tom Becker 1 month ago
The piece this thread hasn't priced yet is who eats the cost of Sana's fragmentation. When the biggest loads go behind-the-meter, the grid's fixed costs - the poles and wires already sunk - don't vanish, they get spread over fewer kilowatt-hours. Fewer payers, same bill, so residential rates climb for everyone who can't build their own plant.
Delia's $333/MW-day isn't just a signal, it's a regressive tax that lands on households hardest. That's what drags this back to politics: a data centre islanding off is a private optimisation that socialises a cost, and voters feel their power bill long before they notice an interconnection queue.
My bet isn't 2028 acquisitions - it's the first rate case where a regulator makes a hyperscaler pay for the grid it stopped using.
Tom Becker 1 month ago
Fellow traveller on the boring middle, Emma - but let me add the one number that cuts the other way. The thread, mine included, assumes demand is the fixed input and supply (iron, transformers, megawatts) is what's scarce.
PJM just told on itself: it's ratcheting its 2027-on demand forecast "appreciably lower," openly because it no longer believes the data centres get built on schedule - chips, electronics and specialised crews are as queued as the substations. So the binding constraint might not be the grid; it might be that the buildout can't consume the megawatts it reserved.
Delia's cleared price is real. But a reserved megawatt and a drawn megawatt are different objects, and the gap between them is where these forecasts have always gone to die.
Jonas Egede 1 month ago
electrician here, so the boring end of the boring middle lol. everyone's arguing transformers and auctions, fair, but nobody's mentioned the crews. you can have the transformer sat on site and still wait months for people qualified to terminate the HV gear and sign it off. half the lads I trained with went offshore wind or retired. heat pumps, EV chargers, now data halls - all pulling from the same small pool of sparkies.
so the iron Jonas I. talks about is real, but the hands are just as booked. no AI is pulling cable through a substation trench any time soon, I'll tell you that for free.